Algeria's post and telecommunications minister laid the foundation stone for a government-owned AI data centre in the Akid Lotfi district of Oran. No capacity or cost figures were released; the facility is meant to give researchers, startups and universities access to AI compute. The government says it expects AI to contribute 7% of GDP by 2027.
FiveNines Group will lead design management and permitting preparation for a 20MW AI data centre on the outskirts of Casablanca for Nexus Core Systems, built on NVIDIA's Vera Rubin NVL72 reference architecture. The facility is the first block of the 180MW AI factory that Nexus agreed with Moroccan agencies in April 2026 and plans to deliver next year. Investment for the 20MW phase was not stated.
Stellarix, the data centre business of the Axian Group, has added capacity at its Senegal facility, pitching it at sovereign cloud, AI workloads and enterprise hosting. Snef, SERTEM Groupe and Kent Data Centres worked on the build. The announcement gives no megawatt, investment or timing figures, so the scale of the expansion is undisclosed.
Intro Group will put nearly US$270m into the first phase of the 80MW Kemet Data Center in the Suez Canal Economic Zone, which it intends to be the zone's first Tier III facility. According to the ICT ministry, engineering designs are finished and supply contracts for equipment and systems have been signed. No dates were given for later phases.
President Al-Sisi directed more investment in cloud and AI and an expansion of large-scale data centres, alongside a wider 5G rollout and steps to reduce concentration risk in communications networks. The meeting set targets of $8bn in digital exports by 2028 and $12bn in digital outsourcing exports in 2029, and reviewed the Karnak Arabic-language AI programme. No data centre capacity or budget was announced.
Communications minister Solly Malatsi told Parliament the National Data and Cloud Policy was designed to give multinationals the certainty to invest in data centres, with incentives handled by the trade department. He said closer work with host municipalities is needed to avoid delays that could deter investment. President Ramaphosa had said in July that hyperscalers have put well over R35.8 billion into local cloud and data centres.
The Ethiopian Artificial Intelligence Institute is courting high-performance computing, cloud and AI infrastructure on the strength of cheap renewable power: the country has 9,760MW installed, about 96% hydro, with 5,150MW at GERD alone. The analysis notes that existing facilities from Raxio and RedFox at the Ethio ICT Park are far below hyperscale, that being landlocked leaves Ethiopia without direct subsea cable access, and that no major hyperscaler has publicly committed. It frames the push as positioning rather than a secured investment pipeline.
Côte d'Ivoire's first state-owned national data centre, under construction in the VITIB zone at Grand-Bassam, is reported on track to open in 2027 with 1.73MW of IT load, 3MW of total power, 228 racks and 10PB of storage. Washington-based Cybastion leads the build with Ivorian contractor Porteo Group and Cisco, HPE and Schneider Electric as technology partners, backed by a $66.1m US EXIM guarantee approved in August 2025 within a $170m package. Construction had passed 20% by December 2025, and the site joins a private market that already includes Equinix, PAIX, Stellarix, Raxio and ST Digital.
Communications and IT Minister Angela Kairuki says Tanzania intends to build AI data centres and is seeking international partners for infrastructure, skills and financing, citing clean electricity and adequate water as advantages. She spoke at the 2026 KOAFEC ministerial conference in Seoul, where about US$2.5 million has been secured through the South Korea partnership, including support for a digital technology university at Nala in Dodoma. No site or budget for the AI data centres was given.
Telekom Networks Malawi has bought the OCL data centre in Kanengo, Lilongwe, to expand its enterprise offering, including data centre as a service. The operator says the facility will also carry its Mpamba mobile money platform and planned AI services. Neither the price nor the site's capacity was disclosed.
Digital Parks Africa, part of the Master Power Technologies group, announced Nigeria Data Centre 1, a carrier-neutral Lagos facility for banks, cloud and connectivity providers, at ITW Africa on 8 September 2026; capacity, cost and timeline were not disclosed. The report sets it against a Lagos pipeline of about 146MW and a Central Bank of Nigeria directive that payment data generated in Nigeria be stored locally, with full compliance due on 1 January 2027.
Vodafone Egypt and Cassava Technologies launched what they call Egypt's first sovereign AI factory, offering NVIDIA GPU capacity as a service with data kept inside Egypt. It sits within Vodafone Egypt's plan to spend more than EGP 20bn this fiscal year. GPU count, site and project cost were not disclosed.
Vodafone Business, Elsewedy Electric and Cassava Technologies are forming Africa Data Centers Egypt, starting at 20MW and planned to grow to 200MW for AI workloads. ICT minister Raafat Hindy expects about US$200m in the first phase rising to US$1bn at full build, with Elsewedy bringing energy and construction capability. The minister also said a national data centre strategy is being prepared.
Digital Realty has opened NBO2, a 6.2MW facility beside its existing NBO1 on a Nairobi campus planned for 34,000 square metres, with up to 4,000 square metres of IT space in the new building. The site connects to more than 100 networks, two internet exchange points and a satellite teleport for backup. The former iColo business now trades under the Digital Realty brand in Kenya and Mozambique. Mordor Intelligence puts Kenya's total data centre capacity at 15MW in 2025, forecast to reach 25MW by 2030.
Nigeria's Ministry of Communications, Innovation and Digital Economy has launched a National Digital Cloud Policy that seeks US$750 million of private investment within 24 months and aims to make the country a West African cloud and hosting hub. It covers data centres, cloud and AI compute, applies sovereignty rules to defined categories of government and regulated data, and proposes a National Digital Marketplace to pool ministries' cloud buying. Rollout runs in three phases over two years, alongside Project BRIDGE.
Lesotho's ICT ministry and the UN ran a five-day workshop in Maseru from 17 to 21 August 2026 to draft a National AI Strategy and a Data Centre Blueprint for secure, resilient data infrastructure. The work builds on AI, data management, and broadband and shared infrastructure policies validated in 2025. The Deputy Prime Minister urged building safeguards, capacity and infrastructure before scaling AI investment.
A mid-term review of Congo's digital plan finds that the network has grown faster than its use. WACS (2012) and 2Africa (2023) land at Matombi, an operator-funded backbone runs Matombi to Pointe-Noire to Brazzaville, the regulator ARPCE runs a Pointe-Noire data centre, and the Central African Backbone already reaches Gabon and CAR with the Cameroon link still being built. Meanwhile e-government services remain largely undigitised, though mobile data volumes grew more than 40% year on year.
Eskom's chairman says the utility has surplus power it cannot sell and is courting US tech firms, but Teraco argues the binding constraint is grid access and wheeling rather than generation. Teraco, at roughly 189MW of critical load, has a 120MW solar plant due for commissioning in Q4 2026 plus NOA wind PPAs, expects new renewables to cover over half its use by end-2027, and wants Eskom to carry power it contracts elsewhere. Any data centre tariff class would need Nersa approval after public consultation, and Teraco expects local AI demand to be mostly smaller inference clusters.
Equinix is taking its Johannesburg 1 site in Germiston, opened in 2024 on a $160m investment, from 4MW to 24MW through two further 10MW phases, with the facility designed for AI loads including liquid cooling. The company has set aside R7.5bn for South Africa overall and bought more land in Johannesburg and Cape Town earlier in 2026, though its local MD says nothing is being built on those plots yet and further capacity depends on customer demand.
The City of Cape Town has cleared two hyperscale campuses drawing roughly 174MW combined, among the largest new individual loads on the African grid. The approvals land against McKinsey projections that continental installed capacity grows from about 0.4GW today to 1.5–2.2GW by 2030, needing an estimated $10–20bn of investment.
Cloud provider Bubble, the first company licensed by INTIC in the advanced category, will run two availability zones, one in Maputo City and one at Beluluane in Maputo Province. The company says the dual-site setup improves continuity and keeps customer data and applications in the country.
South Africa hosts about 70% of Africa’s data centres and has drawn commitments from Microsoft and Amazon, with the market expected to roughly double to $5bn by 2031. Reuters reports the build-out is colliding with the country’s electricity and water constraints, raising the question of whether new load competes with households already exposed to outages and drought.
Raxio Group plans to open TZ1 on the outskirts of Dar es Salaam this year, billed as Tanzania's first carrier-neutral Tier III facility, with 6MW of IT load, 800 racks and a 4,000 square metre footprint, joining 11 existing data centres in the country. Raxio says it will use the SEACOM and EASSy cables to sell IP transit to landlocked neighbours, and reports signing six times as many power contracts in the first half of 2026 as in all of 2025. Shareholders Meridiam and Roha have lifted Raxio's funding pool to US$380 million.
Axian group data centre operator Stellarix says its operations in Madagascar, Tanzania and Senegal now hold ISO 9001, ISO 22301 and ISO/IEC 27001 certification, covering colocation, cloud, managed connectivity and cybersecurity. No site capacities were disclosed.
A BMI (Fitch Solutions) note counts 14 data centres in Morocco with just 1.5MW in operation at Q2 2026, against 140MW under construction and 400MW in planning, concentrated in Casablanca-Settat and Rabat-Sale-Kenitra. BMI projects cloud spending of $981m by end-2026 and about $2.7bn by 2031, driven by the 2021 rule keeping sensitive data in-country and national AI plans. It names grid limits and execution risk as the main constraints, partly offset by rules allowing on-site renewable self-consumption.
ST Digital opened a sovereign Tier III facility in the Nkok Special Economic Zone near Libreville, with about 1MW of power, 92 racks and capacity for roughly 3,000 servers, on an investment of 8bn CFA francs. Around 95% of data generated in Gabon has been hosted abroad, and the ICT ministry signed an MoU giving startups discounted access.
President Tebboune opened Algeria's National Digital Services Center at Mohammadia (Algiers) during the 64th Independence Day celebrations. It runs as two interconnected state data centres, one in Algiers and one in Blida, built to host critical national data in-country with real-time synchronisation and disaster recovery. The state broadcaster cites a 99.98% availability target but gives no capacity, cost or builder.
Mauritania launched a national government cloud on 29 June 2026 at the Tier III National Data Center in Nouakchott, built under the WARDIP programme, to give ministries pooled network, server, storage and application resources instead of separate IT estates. The digital ministry has not set a timeline for migrating government systems, nor disclosed storage capacity or total cost. Its 2026 budget is $24.2 million, up 104.6% on the prior year, and talks are under way with the Islamic Development Bank on a further $50 million.
Airtel is putting $120m into a 38MW facility at Eko Atlantic, designed for AI compute rather than general cloud storage, and targeted to be operational by the end of 2026. It would be the largest data centre in Nigeria and the first of five hyperscale sites the group has flagged for Africa.
The National Telecommunications Regulatory Authority granted Hassan Allam Digital Infrastructure a licence to build and operate data centres and sell cloud services, with $400m committed to the first phase. It is the tenth such licence issued in two years, aimed at serving government and enterprise demand onshore.
With roughly 406MW of total generation, Rwanda would see a single 100MW AI facility absorb nearly a third of its supply, so experts quoted in this piece argue for small modular edge data centres sited near geothermal or solar plants. It counts three operational data centres in Rwanda against 19 in Kenya and 11 in Tanzania, and cites an estimate of just 30MW of live data centre load across East Africa in 2025. One analyst puts the May 2026 rental price of an NVIDIA H100 in Africa at about $13.55 an hour, roughly 85% above the global average.
Prime Minister Abdelhamid Dbeibah launched Libya's National AI Strategy 2026-2030 alongside an AI ethics charter. Targets include AI use in 80% of public institutions, digital ID for 70% of the population, 10,000 civil servants trained, support for 100 AI start-ups and 50% of administrative transactions automated. The strategy is framed around building digital infrastructure and national skills.
Kigali's Broadband Systems Corporation and Oman Data Park have signed an MoU to co-invest in an AI-ready Tier III data centre in Rwanda, aimed at cloud services and data-intensive workloads. The signing was witnessed by ICT ministry officials, including ministers Paula Musoni and Yves Iradukunda, and RISA chief Antoine Sebera. No capacity, investment amount or completion date was given.
SMART Zambia, the government's e-government coordinator, signed an MoU with Huawei at the 2026 Zambia Mobile Congress in Lusaka to jointly back a National Artificial Intelligence Data Centre. The deal also commits to training 5,000 Zambian ICT professionals by 2028 through Huawei's academy programme. No capacity, budget or site was disclosed, so the facility remains at the intent stage.
Togo's state-owned Société d'Infrastructures Numériques (SIN) has partnered with ST Digital to sell private cloud and AI services from the Lomé Data Centre, keeping local companies' data hosted and processed in Togo. The site holds Uptime Institute Tier III certification and reports 99.982% availability. SIN says the offer is meant to reach smaller clients that cannot afford even half a rack, and the partners plan continuing training for local staff.
Mozambique put a draft National AI Strategy out for public consultation from 4 May to 4 June 2026, presented by INTIC chair Lourino Chemane at an ITU workshop. He pitched the country as a regional data centre and cloud hub, citing generation capacity, water, a long coastline for cable landings and a young workforce. The government has also passed new cybersecurity and cybercrime laws.
Kasi Cloud has completed LOS1, the first phase of its campus on four hectares at Maiyegun in Lekki, and moved it into commissioning; construction began in 2022 and the full site is designed for about 100MW of IT load. The company points to proximity to six cable landing stations, including Equiano and 2Africa, and to cloud policy rules on in-country hosting of sensitive government and financial data. LOS1's own capacity and the investment were not stated.
The AI Skills and Compute Africa Foundation has launched in Kigali with undisclosed seed funding from Cassava Technologies, which is also its technology partner for localised sovereign compute. The foundation targets compute grants for 25,000 innovators, support for 10,000 AI researchers and AI-related opportunities for 1 million young people. No GPU count or hardware deployment was specified at launch.
Uganda has launched feasibility and environmental studies for a 400MW run-of-river hydropower station on the Victoria Nile at Kiba, with the timeline cut from 18 to 14 months. Officials say proposed data centre projects alone have lodged requests for 887MW of electricity, against dependable firm capacity of about 1,450MW and a February 2026 peak of 1,337MW. The government projects a 40MW supply deficit in 2025/26 rising above 217MW by 2027/28 unless new generation is accelerated.
President William Ruto said the geothermal-powered campus planned with Microsoft and Abu Dhabi’s G42 would draw about a third of Kenya’s roughly 3,000MW of installed generation. His framing was blunt: switching the site on would mean switching off power for half the country, leaving the project unlikely to proceed as designed.
ARCEP Bénin's 2025 annual report shows the aerial FTTH distribution network growing from 2,079km to 3,266km in a year, with fixed internet subscriptions rising 163.51% to 105,715, of which 95,354 (90.2%) are fibre to the home. State operator SBIN invested 35.880bn FCFA across fixed and mobile networks in 2025, and the wholesale capacity market grew 46.8% to 18.266bn FCFA. The base is still tiny: fixed internet reaches 0.80% of roughly 13 million people, against 64.9% mobile internet penetration.
Communications Minister Salima Monorma Bah said about US$400 million has gone into Sierra Leone's ICT sector, yet a 60% gap remains between network coverage and actual use. The national fibre backbone now reaches 14 of 16 districts, and the country is preparing to land a second subsea cable backed by a US$15 million investment. She pressed operators to share more infrastructure to bring costs down.
President Adama Barrow inaugurated QGroup House, an eight-storey smart building containing what is billed as The Gambia's first data centre, calling it a strategic national asset that lets the country hold its data within its borders. The launch also introduced the QFiber broadband service for homes and businesses, with Huawei cited as QCell's long-time technology partner. Capacity, tier, power arrangements and investment were not disclosed.
BoFiNet's CEO urged state bodies and private firms to host data at its Digital Delta Data Centre, a Tier III certified, carrier-neutral facility, citing Botswana's Data Protection Act, sovereignty and cost. Government has already decided to move critical services there, and BoFiNet says the site offers 99.982% availability. It pitched local hosting to banks, fintechs and regional operators rather than duplicating infrastructure.
President João Lourenço opened Angola's government Data Center and Cloud at Camama, Luanda, on 28 April 2026, a US$89m build delivered with Presight, the G42 group company. The 860 m2 facility holds 208 racks, can run up to 13,000 virtual servers, and is tied to ministries and the National Assembly over a 50 Gbps fibre ring. The government says it will host more than 80 digital public services and also sell capacity to domestic and foreign companies.
Balancing Act's African Interconnection Report, commissioned by WIOCC, finds planned carrier-neutral data centres in sub-Saharan Africa fell from 38 to 23, while existing facilities slipped from 75 to 72 and country coverage stalled at 21. It blames smaller operators struggling to sign tenants, weak francophone demand outside Cote d'Ivoire, financing tied to sales milestones, and delays from governments and elections, while consolidation grows. The report also says the Microsoft and G42 Kenya project was pushed back after seismic issues at its Rift Valley site and may move to Nairobi, and that large Nigerian builds have yet to turn into orders.
Burundi validated a 2025 to 2030 national AI strategy on 22 April 2026, drawn up by the finance and digital economy ministry with UNDP support. Its infrastructure pillar calls for modernising data centres, creating sector hubs, developing sovereign cloud and extending telecom networks, but no capacities, sites or dates are given. The plan also targets training over 1,000 civil servants and about 15 pilots in health and agriculture, against weak data availability and interoperability.
The Bank of Ghana's Cyber and Information Security Directive 2026, launched in Accra in late March to replace the 2018 framework, requires core systems and critical customer data to stay inside Ghana and limits cloud hosting to non-sensitive, front-end services. It applies across banks, microfinance firms, fintechs, savings and loans companies and payment service providers, and extends the sector security operations centre FICSOC to non-bank institutions for the first time. Techlabari notes that many institutions run on AWS, Azure or Google Cloud from outside Ghana, so the rule implies significant re-hosting; the article gives no compliance deadline.
Mauritius launched a National AI Strategy and FAIR ethical guidelines in Phoenix on 9 April 2026, developed by the ICT ministry's AI Unit with UNDP support. Minister Avinash Ramtohul presented AI adoption across priority sectors as a driver of competitiveness and of local firms' regional expansion. The coverage gives no compute, data centre or funding commitments.
The Nexus AI Factory, backed by Nexus Core Systems, Nvidia, Naver and Lloyd Capital, will sit outside Casablanca and serve EMEA. It opens with 40MW of AI compute on Nvidia Blackwell GB200 hardware and is planned to reach 500MW on renewable supply from TAQA.
Oracle launched a public cloud region hosted by N+ONE Datacenters in Casablanca, the first full hyperscaler region in North Africa, with a second planned for Settat. It moves Morocco from "hyperscaler-adjacent" to hyperscaler-present, the shift that separates the top of this index on connectivity from the rest.
Equinix plans more South African data centres under a R7.5 billion (US$438 million) programme pitched at AI demand, having bought further land in Johannesburg and Cape Town totalling 327,000 square metres. The company plans 160MW of additional capacity in the country and funds its South African build from its own balance sheet. Across Africa it reports 409MW operational and 172MW under construction, and it opened a purpose-built Lagos site at the end of 2025. No completion dates were given; the figures come from an Equinix interview with Bloomberg.
Neutral data centre operator Wingu Africa has launched its Wingu Cloud Exchange (WCX) in Ethiopia, a locally hosted private cloud offering compute, storage, Kubernetes container management and security that can run alongside on-premises systems and global clouds such as Azure and AWS. Wingu pitches local-currency pricing as a way for customers to avoid foreign exchange uncertainty, and positions the in-country platform as a route to meeting data sovereignty rules. WCX first launched in Tanzania in November 2025; no pricing, capacity or customer figures were disclosed.
Ghana's Cabinet has approved US$250 million for a national AI compute centre, Communications and Digital Technology Minister Samuel Nartey George told a UNESCO-backed AI readiness forum in Accra on 31 March 2026. Cabinet also cleared a National AI Strategy due for launch on 24 April, with AI research and computing infrastructure among its four priorities. The report gives no financing breakdown, site, capacity or construction timeline for the centre.
A World Bank mission held a mid-term review of PAFEN, Burundi's US$92 million Digital Economy Foundations Support Project launched in 2024, finding 61% of the budget committed. Alongside a national digital ID and public finance tools, the project includes building a national data centre, and the review aimed to find what is slowing delivery ahead of a 2028 target. The report gives no capacity, site or timetable for the data centre.
Cassava Technologies has put its first Nvidia-based AI factory into service inside its South African data centres and plans further AI infrastructure in Nigeria, Kenya, Egypt and Morocco. South Africa's CSIR is an early user, and Cassava says it will offer local-language services starting with Swahili before adding Zulu and Afrikaans. The rollout sits on its CAIMEx model exchange launched in November 2025; Nvidia is also an equity investor in Cassava. No investment figure or GPU count was disclosed.
President Mnangagwa launched Zimbabwe's National AI Strategy for 2026 to 2030, which sets goals for high-performance computing, sovereign data platforms and data centres alongside a phased national AI and data platform. It creates an implementation agency, a regulatory sandbox and a digital regulatory committee reporting to POTRAZ. The report notes power outages and connectivity as current constraints, with tech firms turning to solar and storage, and skills flight as a risk.
Guinea's national data centre in Conakry, inaugurated some months earlier, has finished construction and is moving into operations, with the Corex group in talks with the state to run and maintain it. The site has two grid feeds from opposite sides of the city plus generator backup, but both feeds were down when Le360 visited, and engineers named unreliable electricity as the main risk alongside ageing equipment and round-the-clock staffing. No capacity or cost figures were given.
Centenary Group's technology arm, Cente-Tech, is finishing a Tier III-ready data centre in Masaka, about 130km from Kampala, with civil works and installation complete and opening set for September 2026. The open-access site will host Centenary Bank's 3 million account holders plus government and enterprise clients and provide an internet point of presence; the operator says its solar-assisted design uses 40% less power than conventional builds. Tier III certification is still being sought, and capacity and cost were not disclosed.
Equity Bank Uganda has moved its core data centre operations to Raxio's Tier III facility in Namanve Industrial Park, completing the cutover in February 2026 and unveiling it on 25 February. The bank, which has more than 2 million customers, says local hosting cuts latency and strengthens disaster recovery, though customers lost access to services for two days during the switch. Bank of Uganda's supervision chief framed in-country digital infrastructure as a financial stability matter.
Open Access Data Centres, part of WIOCC Group, has bought seven NTT DATA facilities in Bloemfontein, Cape Town, East London, Bryanston, Parklands, Gqeberha and Umhlanga, closing on 31 December 2025 after Competition Commission approval. The deal is a sale and leaseback: OADC owns and runs the buildings while NTT leases them back and keeps its customers. It takes OADC's South African capacity past 25MW; terms were not disclosed.
Kasi Cloud, backed by Nigeria’s sovereign wealth fund, is building a $250m hyperscale campus in Lekki against a grid that has never sustained more than about 6GW for 230m people. Diesel backup puts operators near $0.40 to $0.50 per kWh where competing markets pay $0.05 to $0.10, which is the gap the 320MW national pipeline has to absorb.
National Treasury has elevated data centre infrastructure to the same strategic tier as electricity, ports and transport, and is examining incentives to support the build-out. Around 55 facilities are already operating, with more than R50bn of investment expected over three years as Microsoft, Google and AWS expand cloud and AI capacity in the country.
This analysis argues Uganda risks remaining a consumer of foreign AI because it has only about four data centres (Raxio in Namanve, MTN's facility and government sites including NITA-U's National Data Centre). It points to Synectic Technologies' planned Aeonian hyperscale and HPC campus drawing 100MW of surplus power from the 600MW Karuma hydro plant, including a 30MW AI facility, and to new rules requiring organisations to keep data in-country. Industry voices quoted call for private hyperscale-grade investment and policy and finance support.
MTN Group chief executive Ralph Mupita said MTN will reinvest about US$1.1 billion in Ghana over three years, spread across network resilience, 4G and 5G expansion and large-scale data centres to support AI and cloud ambitions. He argued that hyperscale capacity and better use of subsea cable bandwidth could make Ghana a competitive West African hub, though no data centre sites, sizes or dates were named.
Converged Technology Networks plans what it calls Malawi's first micro data centre, built for AI workloads, with NVIDIA A100 GPUs to be installed within months and rented out on a GPU-as-a-service basis. The company will work with Africa GPU Hub and offer free GPU credits to local researchers and students. Despite the headline, the piece describes a plan rather than a running facility, and gives no investment or capacity figures.
The two are planning a $250m facility at Maadi Technology Park with about 25MW of IT load, which would be the country’s first hyperscale-class site. It marks Gulf operator capital entering the Egyptian market directly rather than through a local reseller.
Cavaleros has plans for 360MW in Cape Town and 200MW north of Johannesburg, while Teraco is targeting 500MW in total, 290MW of it new in Johannesburg. Together the announced pipeline adds roughly 1,000MW to national demand, about one stage of load shedding, and points to a supply squeeze by 2029 unless generation grows with it.
Chad's ICT agency ADETIC and cyber-security agency ANSICE hired TECHSO-GROUP on 5 February 2026 to audit the national data centre, the last step before it opens. The four-level, 500 m2 facility is designed for more than 500 servers and close to 2 million electronic transactions a day. It is part of the roughly EUR175.1m state connectivity programme.
Mali's digital ministry inaugurated a Tier III national data centre during the country's third Digital Week, with digital ministers from the Alliance of Sahel States in attendance. It will host state data, e-government platforms and public digital services and, in the near term, shared digital infrastructure for the AES bloc that also includes Niger and Burkina Faso. No capacity, cost, site or vendor details were published.
iXAfrica will act as host partner for an Oracle Cloud Infrastructure region in Nairobi, the country’s first public cloud region. It sits on a 22MW hyperscale, carrier-neutral campus built for AI workloads and tied to renewable supply, which moves latency-sensitive workloads onshore for the first time.
Prime Minister Rimtalba Jean Emmanuel Ouédraogo opened two modular government-cloud data centres in Ouagadougou costing over CFA 15 billion, part of a policy of keeping no public data abroad. Officials cite 3,000TB of storage, 105,600GB of memory and 28,800 CPU cores, enough for more than 7,000 virtual machines, and project net savings of CFA 85 to 95 billion over ten years. A larger national data centre built to international standards is planned by 2028.
India's state-owned RailTel will build a greenfield data centre for Ethiopia's Ministry of Foreign Affairs inside the ministry's existing Addis Ababa building, in a deal valued at roughly US$2.2 million and secured with backing from India's Ministry of External Affairs. The build is due within a year, followed by three years of operation and maintenance after go-live. RailTel has not disclosed the facility's size or IT capacity; the project is framed as support for the Digital Ethiopia 2030 strategy.