Congo : Le nouveau datacenter national livré d'ici la fin de l'année 2026
Congo's national data centre in Bacongo, Brazzaville, built by China's Sumec, is now promised by end 2026 after work stopped in October 2025 at about 95% complete because the state ran short of funds. The building is designed to Tier III-level availability (99.98%), with three 3,000 kVA generators giving 72 hours of autonomy and a hybrid grid and solar supply under study. It belongs to the Central African Backbone programme, a CFA43.65bn envelope co-financed by the AfDB and the Congolese state.