A Central Bank of Nigeria circular issued in June 2026 requires banks, fintechs, mobile money operators and other payment service providers to store and manage payment transaction data generated in Nigeria inside the country, with full compliance due by 1 January 2027. A NITDA and CBN survey cited by Nairametrics found only 59% of financial institutions ready, and smaller payment firms and microfinance banks may miss the date; the CBN's payments supervision director said sanctions will follow deliberate non-compliance. Local operators Digital Realty Nigeria and Rack Centre are positioning for the migration, with Digital Realty arguing the rule should cover where data is processed, not only where it is stored.
Kasi Cloud has completed LOS1, the first phase of its campus on four hectares at Maiyegun in Lekki, and moved it into commissioning; construction began in 2022 and the full site is designed for about 100MW of IT load. The company points to proximity to six cable landing stations, including Equiano and 2Africa, and to cloud policy rules on in-country hosting of sensitive government and financial data. LOS1's own capacity and the investment were not stated.
Balancing Act's African Interconnection Report, commissioned by WIOCC, finds planned carrier-neutral data centres in sub-Saharan Africa fell from 38 to 23, while existing facilities slipped from 75 to 72 and country coverage stalled at 21. It blames smaller operators struggling to sign tenants, weak francophone demand outside Cote d'Ivoire, financing tied to sales milestones, and delays from governments and elections, while consolidation grows. The report also says the Microsoft and G42 Kenya project was pushed back after seismic issues at its Rift Valley site and may move to Nairobi, and that large Nigerian builds have yet to turn into orders.
Equinix plans more South African data centres under a R7.5 billion (US$438 million) programme pitched at AI demand, having bought further land in Johannesburg and Cape Town totalling 327,000 square metres. The company plans 160MW of additional capacity in the country and funds its South African build from its own balance sheet. Across Africa it reports 409MW operational and 172MW under construction, and it opened a purpose-built Lagos site at the end of 2025. No completion dates were given; the figures come from an Equinix interview with Bloomberg.
Cassava Technologies has put its first Nvidia-based AI factory into service inside its South African data centres and plans further AI infrastructure in Nigeria, Kenya, Egypt and Morocco. South Africa's CSIR is an early user, and Cassava says it will offer local-language services starting with Swahili before adding Zulu and Afrikaans. The rollout sits on its CAIMEx model exchange launched in November 2025; Nvidia is also an equity investor in Cassava. No investment figure or GPU count was disclosed.
Kasi Cloud, backed by Nigeria’s sovereign wealth fund, is building a $250m hyperscale campus in Lekki against a grid that has never sustained more than about 6GW for 230m people. Diesel backup puts operators near $0.40 to $0.50 per kWh where competing markets pay $0.05 to $0.10, which is the gap the 320MW national pipeline has to absorb.
TechCabal counts 17 operating data centres in Nigeria with at least nine more under construction or planned, and puts installed capacity at 65 to 86MW, which industry projections see passing 400MW within three to five years. It names Kasi Cloud's $250m Lekki campus (a first phase of 32 to 44.4MW, racks up to 100kW) and Airtel's $120m Nxtra build in Lagos as the likeliest first AI-grade facilities. Operators quoted say imported equipment, currency swings and reliable power remain the binding constraints, and many projects are still being redesigned.
LG3 is the opening phase of a roughly $100m two-year African programme, with the Lagos site slated to open in Q1 2026. Separately Rack Centre began hosting EdgeNext’s CDN and cloud services locally, shortening delivery routes for gaming, fintech and content workloads.
Equinix, Kasi, Nxtra by Airtel and OADC are all building close to the eight subsea landing stations on Lagos Island, buying short routes to international capacity and access to cooling water. Nigerian capacity is expected to move from about 64MW to roughly 200MW by 2027, second on the continent behind Johannesburg.
Open Access Data Centres, part of WIOCC Group, set out a $240m multi-phase expansion of its Lagos facility to 24MW, the first 12MW due in 2026. The spend sits inside a wider $500m African build programme aimed at cloud, analytics and AI demand.